Quarantine Did Not Affect the Plans to Complete the CSFN
The final works on the construction of the Centralized Spent Fuel Storage Facility are planned to be completed by December 31, 2020. NAEK Energoatom announced the relevant tender in February and will accept applications until April 9.
The auction under the tender “Works on Completion of Construction on the Ste: Centralized Storage of Spent Nuclear Fuel of WWER Reactors of NPPs of Ukraine” is scheduled for May 15, 2020. The expected cost of the works is UAH 655.8 million.
As Energoatom’s spokeswoman Ilona Zayets said in a comment to Ukrainian Energy, that an additional tender is needed to include works that were not taken into account in the main contract.
According to her, quarantine due to the spread of coronavirus did not affect the construction process.
«Currently, preparatory works are underway at the NPP — in the regular mode. So the quarantine did not affect,» said Zayets.
Construction of a centralized storage facility for spent nuclear fuel in the Chornobyl Exclusion Zone began in April 2017. The construction work was expected to be completed in the first quarter of 2020, and the commissioning of the storage facility will begin in April.
Spent fuel from Rivne, South-Ukrainian and Khmelnytsky NPPs will be stored at the CSFF.
Simultaneously, Energoatom provides nuclear modifications of station equipment at nuclear power plants according to Holtec International technology.
According to Ukrainska Energetyka
An Exhibition Highlighting Chornobyl’s Lessons and Modern Challenges Presented in the Kyiv
The art and technology exhibition «Chornobyl. 40 Years After. A...
Read more
SSTC NRS presented Nikolai Steinberg’s book «Our Long Road to April»
On April 22, the presentation of Nikolai Steinberg’s book «Our...
Read more
The Chornobyl Disaster: 40 Years of Remembrance and Responsibility
April 26, 1986 was the day that the worst man-made...
Read more
Chornobyl. A Look Through the Years
Introduction The accident at Chornobyl NPP Unit 4, one of...
Read more